Fire load density: category C1–C4

Enter the mass of each combustible in the room, the area it occupies and the clearance to the ceiling. The tool computes the fire load density and the C1–C4 category.

Updated Technical review: KS. Dương Văn TiếnFree, no sign-up
Quick answer

Total heat 67,000 MJ, fire load density 670 MJ/m²: room category C2 (High fire hazard).

Inputs

m²
At least 10 m²
m
Used for the C2/C3 upgrade check

Combustible masses

kg
kg
kg
kg
kg
kg
kg
kg
kg
kg
kg
MJ/kg

Enter your data, then press Calculate (or Enter).

Preliminary results

Total heat67,000MJ
Fire load density670MJ/m²
CategoryC2
StepResultBasis
Paper, cartons5,000 × 13.467,000 MJ—
Total heatQ = Σ Gᵢ·Qᵢ67,000 MJSP 12.13130 PL B · QCVN 06:2022 ⚠
Fire load densityg = 67,000 / 100670 MJ/m²SP 12.13130 PL B · QCVN 06:2022 ⚠
Category by gg = 670C3SP 12.13130 PL B · QCVN 06:2022 ⚠
Upgrade check Q ≥ 0.64·g_T·H²0,64 × 1400 × 4.0² = 14,336Q ≥ … → C2SP 12.13130 PL B · QCVN 06:2022 ⚠
Sources and assumptions. Q = ΣGᵢ·Qᵢ, g = Q/S (S ≥ 10 m²); C1 > 2,200, C2 1,401–2,200, C3 181–1,400, C4 1–180 MJ/m²; C2, C3 upgraded when Q ≥ 0.64·g_T·H² (SP 12.13130 Annex B, applied for QCVN 06:2022/BXD categories) ⚠. Material heat values are reference values ⚠. C4 rooms also limit each load patch to ≤ 10 m² with spacing. ⚠ = code table value to be checked against the original standard. Preliminary results for material selection and budgeting; not a substitute for an approved fire protection design.

Fire load density thresholds

Categoryg, MJ/m²Hazard
C1> 2,200Highest fire hazard
C21,401–2,200High fire hazard
C3181–1,400Medium fire hazard
C41–180Low fire hazard

Frequently asked questions

What category is a 100 m² paper store with 5 t of goods?

Q = 5,000 × 13.4 = 67,000 MJ, g = 670 MJ/m² → C3; with a small ceiling clearance (4 m: 0.64 × 1,400 × 16 = 14,336 < 67,000) it is upgraded to C2.

What is fire load used for?

The room C1–C4 category drives the building class (A–E), required fire resistance, compartment size and sprinkler and smoke control needs.