Fire safety advisor for factories, warehouses and buildings

Enter length × width × height or floor area, pick (or type) the business activity and the building structure. The tool infers the fire hazard class and fire resistance, checks design appraisal under Appendix III of Decree 105/2025/ND-CP (replaced by Decree 347/2026/ND-CP) and proposes a solution for each system with rough quantities.

Updated Technical review: KS. Dương Văn TiếnFree, no sign-up
Quick answer

Timber, plywood, pallet warehouse, 2,000 m² floor, 14,000 m³, unprotected pre-engineered steel frame, metal roof: class C, fire resistance IV. Fire design appraisal: required. Automatic fire alarm: verify ⚠. Automatic sprinklers: verify ⚠.

Inputs

Pick from the list or type, e.g. "timber warehouse", "metal workshop", "garment factory"
Pick or type, e.g. "pre-engineered steel", "reinforced concrete", "EPS panel"
m
m
m
Floor to roof ridge
m²
Used when length × width is blank
Appendix III note: if so, this item must be appraised too

Enter your data, then press Calculate (or Enter).

Preliminary results

Design appraisalRequired
Fire hazard classC
Fire resistanceIV
Total floor area2,000m²

Volume: 14,000 m³ · Timber, plywood, pallet warehouse · Unprotected pre-engineered steel frame, metal roof

Against thresholds
CriterionProjectThresholdResult
Total floor area (m²)2,000≥ 2,000Met
Volume (m³)14,000≥ 15,000Not met
Sources and assumptions. Basis: Law on Fire Prevention, Fighting and Rescue 55/2024/QH15; Appendix III of Decree 105/2025/ND-CP, replaced by Appendix III of Decree 347/2026/ND-CP (effective 15/09/2026). Summaries state Decree 347/2026 keeps the storey, area and volume thresholds; values come from excerpts and are marked ⚠ pending the official text. Building hazard class per QCVN 06:2022/BXD. Results guide the procedure and do not replace the appraising authority. ⚠ = code table value to be checked against the original standard. Preliminary results for material selection and budgeting; not a substitute for an approved fire protection design.

Recommended solution

ItemVerdictProposed solutionBasis
Fire safety design appraisalRequiredMeets the threshold of item 10: 2,000 m² floor (threshold 2,000) or 14,000 m³ (threshold 15,000). Prepare the fire design and submit for appraisal before construction: distances, evacuation and compartmentation go with the construction dossier; alarm and suppression go to the police.NĐ 105/2025 PL III mục 10, NĐ 347/2026 ⚠
Structure, fire resistance
Detailed calculation →
UpgradeUnprotected pre-engineered steel frame, metal roof reaches only about grade IV. For a class C building of this size, fire-protect columns and trusses (R45–R90 per design ⚠) or add fire walls to raise the grade and cut fire water demand.QCVN 06:2022/BXD Bảng 4, 6 ⚠
Automatic fire alarm
Detailed calculation →
Verify ⚠Table A.1 of QCVN 10:2025/BCA has no row for a single-storey class C warehouse; it falls under the production and storage part of Appendix A ⚠. Send drawings to Thep Minh Tien to check.QCVN 10:2025/BCA 2.1, QCVN 10:2025/BCA Phụ lục A ⚠
Automatic fire suppression
Detailed calculation →
Verify ⚠Table A.1 of QCVN 10:2025/BCA has no row for a single-storey class C warehouse; it falls under the production and storage part of Appendix A ⚠. Send drawings to Thep Minh Tien to check. If required: sprinkler group 3, about 167 heads, 28.8 L/s, water 104 m³ ⚠.QCVN 10:2025/BCA 2.5, QCVN 10:2025/BCA Phụ lục A ⚠; TCVN 7336:2021
Indoor fire hydrants
Detailed calculation →
Required2 hydrants × 5.0 L/s, valve and hose DN65, riser DN65, 1-hour water 36 m³ ⚠.QCVN 10:2025/BCA 2.4; TCVN 3890:2023 ⚠
Outdoor fire water
Detailed calculation →
Required25 L/s for 3 hours = 270 m³ (Table H.3). Use a public hydrant within 400 m if it has the flow, otherwise a dedicated tank and hydrants, main DN125 ⚠.QCVN 10:2025/BCA Bảng H.3 ⚠
Fire water tank, pump station
Detailed calculation →
EstimateTotal fire water ≈ 410 m³ (sprinklers + indoor + outdoor hydrants). Pump station: main electric pump, standby diesel pump, jockey pump ⚠.TCVN 7336:2021; QCVN 02:2020/BCA
Portable extinguishers
Detailed calculation →
Required20 extinguishers rated 4A (≤ 100 m² each, travel ≤ 15 m), at least 2 per floor; add CO₂ units at electrical panels.QCVN 10:2025/BCA 2.6; TCVN 7435-1:2004
Emergency lighting, evacuationRequiredEmergency lighting and exit signs at exits and corridors; provide enough exits per QCVN 06:2022/BXD ⚠.QCVN 10:2025/BCA 2.2; QCVN 06:2022/BXD
Acceptance, records
Detailed calculation →
RequiredThe owner carries out acceptance and keeps as-built records; police post-inspect. Managed facilities need a firefighting plan, an in-house fire team and training.NĐ 105/2025 Điều 8; NĐ 347/2026 ⚠

Who appraises, who accepts

TaskByBasis
Appraisal of fire separation distances, fire truck access, evacuation, fire resistance, compartmentation, smoke protectionThe construction authority, together with the construction design dossier. Projects outside its remit are self-appraised by the owner.Law 55/2024/QH15; Decree 105/2025 Art. 8, 9; Law 135/2025/QH15 ⚠
Appraisal of fire alarm, fire fighting systems and fire-service powerPolice: the Fire Police Department or provincial police according to delegation.Decree 105/2025 Art. 9; Circular 36/2025/TT-BCA ⚠
AcceptanceThe owner organises acceptance, signs the record and is responsible. Police inspection of acceptance results has been abolished in favour of post-inspection.Decree 105/2025 Art. 8; Decree 347/2026 repeals Art. 10 ⚠
Projects not listedNo appraisal certificate needed, but design, construction and equipment must still meet the regulations. Facilities in Appendix I of Decree 105/2025 remain subject to periodic fire inspections.QCVN 06:2022/BXD; QCVN 10:2025/BCA; Decree 105/2025 Appendix I

Appendix III: buildings requiring fire safety design appraisal

ItemBuilding typeRequired when
1Apartment buildings, collective housing≥ 7 storeys or ≥ 3,000 m² floor
2Nurseries, kindergartens≥ 2,000 m² floor or ≥ 150 children
2Schools, universities, colleges, vocational and research facilities≥ 5 storeys or ≥ 3,000 m² floor
3HospitalsAny size
3Clinics, health stations, maternity homes, nursing homes, other healthcare≥ 5 storeys or ≥ 2,000 m² floor
4Stadiums≥ 5,000 seats
4Sports halls, training halls≥ 5,000 m² floor or ≥ 5,000 seats
5Theatres, cinemas, circuses≥ 300 seats
5Convention centres, cultural houses, museums, libraries, exhibitions≥ 5 storeys or ≥ 3,000 m² floor
5Dance clubs, karaoke, entertainment venues≥ 4 storeys or ≥ 1,000 m² floor
6Markets, shopping centres, supermarkets, shops selling flammable goods≥ 2,000 m² floor
6Restaurants, eateries≥ 3,000 m² floor
7Hotels, guest houses, accommodation≥ 7 storeys or ≥ 3,000 m² floor
7Post offices≥ 7 storeys or ≥ 3,000 m² floor
7Head offices, office buildings≥ 7 storeys or ≥ 3,000 m² floor
8Multi-purpose, mixed-use buildings (with parts under items 1–7)≥ 7 storeys or ≥ 3,000 m² floor
9.1Refineries, petrochemical, gas processing; fuel and LPG depots; filling stations with 1+ pumpAny size
9.2Power plants; substations 110 kV and aboveAny size
9.3Explosives production and storage, precursors, weapons, support toolsAny size
9.4Production buildings, class A, B≥ 1,000 m² floor or ≥ 7,000 m³
9.4Production buildings, class C≥ 2,000 m² floor or ≥ 15,000 m³
9.4Production buildings, class D, E≥ 10,000 m² floor or ≥ 30,000 m³
10Warehouses, class A, B, C (timber, paper, textiles, plastics, goods in combustible packaging)≥ 2,000 m² floor or ≥ 15,000 m³
10Warehouses, class D, E (steel, metals, non-combustible goods without combustible packaging)Not listed
11Technical infrastructure of urban areas, housing estates, industrial parks and clusters, tourist zonesCheck dossier, construction grade ⚠
12Enclosed car and motorbike parking, enclosed vehicle showrooms≥ 2,000 m² floor
13Airport terminals, aircraft maintenance buildings, control towersAny size
13Inland waterway ports and wharves, seaportsCheck dossier, construction grade ⚠
13Bus stations, vehicle inspection centres, rest stops, vehicle repair buildings≥ 3,000 m² floor
13Railway stations, depots, cable car stations≥ 3,000 m² floor
14Road, rail and metro tunnelslength ≥ 1,000 m
15Buildings of nuclear facilitiesAny size
  • Total floor area is taken for the largest building in the project.
  • If a project has a listed building, its other items with fire requirements must also be appraised.
  • Applies to new construction, renovation and change of use affecting fire safety conditions.
  • Construction grade is determined under construction law.

Frequently asked questions

Does a 2,000 m², 7 m high timber warehouse need fire design appraisal?

Yes. A timber warehouse is class C. Item 10 of Appendix III: class A, B, C warehouses from 15,000 m³ or from 2,000 m² floor area. The volume of about 14,000 m³ is below the limit, but 2,000 m² reaches the area threshold.

Does a large steel warehouse need appraisal?

Warehouses of bare steel and metals without combustible packaging are usually class D or E, not covered by item 10, so not listed regardless of size ⚠. Areas holding plastic pipe, timber or goods in paper or plastic packaging may become class C.

If not listed, is anything required?

Yes. No appraisal certificate, but design, construction and equipment must comply with QCVN 06:2022/BXD and QCVN 10:2025/BCA (see the Required fire equipment tool), and inspections still apply to facilities under fire management.

Who carries out acceptance from 01/07/2026?

The owner organises acceptance and is responsible. Police inspection of acceptance results was abolished in favour of post-inspection ⚠.

Applicable documents

Documents in force at the update date, applied from 1 July 2026. TCVN standards are mandatory only when a QCVN refers to them; where they differ, the QCVN prevails.

CodeTitleEffective fromStatus
Luật 55/2024/QH15Luật Phòng cháy, chữa cháy và cứu nạn, cứu hộ01/07/2025In force
NĐ 105/2025/NĐ-CPChi tiết và biện pháp thi hành Luật PCCC và CNCH01/07/2025In force ⚠
NĐ 347/2026/NĐ-CPSửa đổi NĐ 169/2025, 105/2025, 106/2025, 282/202515/09/2026In force
QCVN 10:2025/BCATrang bị, bố trí phương tiện PCCC và CNCH cho nhà và công trình30/12/2025In force
QCVN 06:2022/BXD + SĐ1:2023An toàn cháy cho nhà và công trình16/01/2023In force ⚠
Luật 135/2025/QH15Luật Xây dựng 202501/07/2026In force
NĐ 217/2026/NĐ-CPQuy định chi tiết Luật Xây dựng về quản lý hoạt động xây dựng01/07/2026In force

See the full list of regulations and standards →